| Province | District | | | |
Construction of Mushindamo Girls Tech Boarding High School | Northwestern | Solwezi | Hua-Jiang Investments | 0.79 | Operational; contractor attending to snags; Sports fields being done. |
Construction of Chavuma Boarding High School | Northwestern | Chavuma | Hua-Jiang Investments | 0.67 | Operational; Contractor working on snags, Sewerline to be redone. |
Construction of Kanyama Boarding High School | Northwestern | Mwinilunga | Hua-Jiang Investments | 0.75 | Operational; Contractor working on snags, connecting water from the river as additional works, and construction of oxidation ponds to be done. |
Construction of Kayombo Boarding High School | Northwestern | Kabompo | China Jiangxi | 0.93 | Operational; Using genset, contractor attending to snags. |
Construction of Mufumbwe Boarding High School (Phase II) | Northwestern | Mufumbwe | Jizan | 0.56 | Operational; Buildings at finishes level and external works yet to be done. |
Construction of Kaputa Boarding High School | Northern | Kaputa | Hua-Jiang Investments | 0.69 | Operational; external works still in progress; Sports fields not yet done |
Construction of Lupososhi Boarding High School | Northern | Luwingu | Hua-Jiang Investments | 0.6 | Operational;Contractor attending to the snags; and also on external engineering services. |
Construction of Chilubi Boarding High School | Northern | Chilubi | Hua-Jiang Investments | 0.7 | Operational; Contractor working on fininishes to the buildings and also constructing external engineering services.. |
Construction of Lunte Girls Technical Boarding High School (Phase1) | Northern | Mporokoso | Wah Kong | 0.92 | Operational;External works still in progress, contractor attending to snags.. |
Construction of External Works at Lunte Girls Technical Boarding High School. | Northern | Mporokoso | Wah Kong | 0.17 | Operational;External works still in progress. |
Construction of Menje Boarding High School | Northern | Mbala | Savenda | 0.63 | Most of houses roofed, learning area buildings at superstructure level. |
Construction External Works at Menje Boarding High School | Northern | Mbala | Savenda | 0.2 | External works in progress. |
Construction of Ntumpa Boarding High School | Northern | Kasama | Hua-Jiang Investments | 0.68 | Operational; Contractor attending to snags.. |
Construction of External Works at Ntumpa Boarding High School | Northern | Kasama | Hua-Jiang Investments | 0.32 | Operational;External works still in progress. |
Construction of Milenge Boarding High School | Luapula | Milenge | Hua-Jiang Investments | 0.82 | Operational; Attending to snags, sports fields not yet done.. |
Construction of Kapale Boarding High School | Luapula | Nchelenge | Hua-Jiang Investments | 0.81 | Finishes and painting works in progress. |
Construction of External Works at Kapale Boarding High School | Luapula | Nchelenge | Hua-Jiang Investments | 0.26 | External works still in progess |
Construction of Kashita Day High School | Luapula | Mwansabombwe | China Gansu Engineering | 0.7 | Operational, external works still in progress. |
Construction of Moomba Boarding High School | Central | Chibombo | Hua-Jiang Investments | 0.63 | Operational; Oxidational ponds and Sports fields not yet done, school negotiating for land.. |
Construction of Kapiri Mposhi Day High School | Central | Kapiri Mposhi | Zaminliny | 0.84 | Operational; Contractor attending to snags, school negotiating for land to build oxidation ponds. |
Construction of Kapiri girls’ Tech School Secondary School | Central | Kapiri Mposhi | Wah Kong | 0.85 | Operational; high iron content in water to be ressolved; sports fields not done. |
Construction of Kafushi Boarding Secondary School | Central | Chibombo | Covec | 0.92 | Operational; Contractor attending to snags; sports fields not done yet. |
Construction of Itezhitezhi Boarding Secondary School | Central | Itezhitezhi | Hua-Jiang Investments | 0.82 | Operational; external works still in progress. Sports fields not yet done. |
Construction of Justin Mukando Boarding High School (Phase 2) | Central | Serenje | Hua-Jiang Investments | 0.62 | Operational; Plumbing works not completed to kitching dining hall, contractor attending to snags, Sports fields not yet completed. |
Construction of Chipepo Secondary School | Central | Kapri Mposhi | Hua-Jiang Investments | 0.9 | Operational; Oxidation poinds excavated not yet lined with concrete;Sports fields in progress, school using genset not yet connected to (zesco) National Grid. |
Construction of Muyombe Boarding High School (Phase 2) | Muchinga | Mafinga | Covec | 0.84 | Operational water, sewer reticulation and oxidation ponds under construction |
Construction of Mandevu Day High School ( in Luangwa) | Lusaka | Luangwa | Datong | 0.87 | Operational; Attending to snags. |
Construction of Kabanana Day Secondary School | Lusaka | Lusaka | ASSESCO | 0.64 | Operational; Attending to snags, external works in progress. |
Construction of Chiware Boarding High School (Phase 1) | Eastern | Nyimba | Wah Kong | 0.68 | Operational; Contractor attending to snags & working on external works. |
Construction of Mutumbata day High School | Eastern | Petauke, | Mango Tree Construction Ltd | 0.62 | Operational; Oxidation ponds under construction. |
Construction of Kapoche Boarding High School | Eastern | Katete | Mango Tree Construction Ltd | 0.78 | Operational; contractor attending to snags. |
Construction of Mumbi Boarding High School | Eastern | Petauke, | Zamchin | 0.53 | Finishes under construction, while external works not yet commenced. |
Construction of Lukulu Boarding High School | Western | Lukulu | China Jiangxi | 0.79 | Operational; Attending to snags, External works in progress |
Construction of Nakaanya Girls Tech Boarding High School | Western | Mongu | Hua-Jiang Investments | 0.92 | Operational; Contractor attending to snags, while external works are still in progress. |
Construction of Nangweshi Boarding High School | Western | Shang’ombo | China Jiangxi | 0.77 | Operational; Contractor attending to snags, external works in progress. Septic & soak aways done, geneset available not installed, sports field not done space not adequate. |
Construction of Munyumbwe Boarding High | Southern | Gwembe | Hua-Jiang Investments | 0.8 | Operational; Contractor attending to snags; Oxidation ponds & sports fields under construction. |
Construction of Batoka Boarding High School | Southern | Choma | Covec | 0.71 | Operational; Contractor attending to snags, sports fields done except football pitch. |
Construction of Musa Day High School | Northern | Kasama | Associated Electrical and Sales Contractors | 0.31 | All buildings roofed, except school hall which is at superstructure. External works not yet commenced. |
Construction of Bweupe Boarding Secondary School | Northern | Mporokoso | Hua Jiang Investments | 0.16 | Most of buildings were at superstructure level. |
Construction of Nsama Boarding Secondary School | Northern | Nsama | Hua Chang | 0.39 | Learning area buildings at superstructure level & some houses have been roofed. |
Mungwi Girls Boarding Secondary School | Northern | Mungwi | African Brothers | 0.35 | All buildings roofed & finishes in progress. |
Construction of Katuta Boarding Secondary School | Northern | Luwingu | Hua Jiang Investments | 0.21 | All buildings at Superstructure level. |
Construction of Kasaba Day High School | Luapula | Samfya | ASESCO | 0.16 | Some buildings roofed, while some at superstructure -level. External works not yet commenced. |
Construction of Kalanga Day Secondary School | Luapula | Mansa | Melt Cast/ Geo tech joint venture | 0.42 | Most building roofed & finishes in progress, while external works not yet commenced. |
Construction of Chembe Boarding Secondary School | Luapula | Cheembe | Powerflex | 0.24 | Almost all buildings were at gable level, while gilrls’ dormitories were roofed. External works not yet commenced. |
Construction of Mweenda Boarding Secondary School | Luapula | Chipili | China Henan | 0.25 | Most buildings were at superstructure level, except assembly hall which was still at substructure level. |
Construction of Pambashe Boarding Secondary School | Luapula | Kawambwa | China Gansu | 0.35 | Most of the buildings were roofed & finishes were in progress. External works not yet commenced. |
Construction of Kalungwishi Boarding Secondary School | Luapula | Chienge | Flourishing | 0.43 | Recommended for termination; some buildings were at superstructure level while others were still at substructure level. Ezxternal works not commenced. |
Construction of Kanona Day High School | Central | Serenje | Savenda | 0.58 | All buildings roofed except, assembly hall still at substructure level. |
Construction of Mumbwa Day High School | Central | Mumbwa | Z-Con | 0.27 | All buildings were at superstructure -level; external works not yet commenced. |
Construction of Chibale Day High School | Central | Serenje | ASESCO | 0.37 | Teachers houses roofed and plastered, other buildings at supperstructure level, except for assembly hall at substructture level. |
Construction of Mailo Boarding Secondary School | Central | Serenje | Savenda | 0.62 | All buildings roofed, excpt assembly hall and dining kitchen. |
Construction of External works at Mailo boarding Secondary School | Central | Serenje | Savenda | 0.21 | External works in progress. |
Construction of Mkushi South Boarding Secondary School | Central | Luano | Savenda | 0.17 | Most buildings were at substructure level , while a few were at superstructure level. External works not yet commenced. |
Construction of Makululu Day Secondary School | Central | Kabwe | BSBK Joint Venture | 0.38 | Operational; All buildings roofed, and external works in progress. |
Construction of Muchinda Boarding Secondary School | Central | Serenje | Saltech Enterprises Limited | 0.2 | Five houses were roofed, while most other buildings were at gable level, except assembly hall which was at substructure level. External works not commenced yet. |
Construction of Fisenge Day High School | Copperbelt | Luanshya | Shaftex | 0.4 | Operational; Most buildings were at finishes level, assembly hall not roofed & external works in progress.. |
Construction of Chati South Boarding Secondary School | Copperbelt | Kalulushi | Plinth | 0.06 | Finishes to building in progress, & external works were in progress. |
Construction of Mulundu Day Secondary School | Copperbelt | Mufulira | Covec Zambia Limited | 0.29 | Most buildings were at superstructure level, except assembly hall which was still at substructure level. |
Construction of Lumpuma Boarding Secondary School | Copperbelt | Lufwanyama | Datong Construction | 0.15 | Most of buildings were at superstructure level while a few were still at substructure level. |
Construction of Luansobe Boarding Secondary School | Copperbelt | Masaiti | Earthrow Investments Limited | 0.19 | Some of builldings were at superstructure level, while others are at substructure level. |
Construction of Munali Centre of Excellence for special education needs | Lusaka | Lusaka | China Jiangxi | 0.5 | some buildings roofed; Others were at gable level while external works were not yet commenced. |
Construction of Faith Baptist Community School | Lusaka | Lusaka | Hua Chang | 0.52 | All buildings roofed & platered; External works in progress. |
Construction of Chikupi Day Secondary School | Lusaka | Kafue | Dong Da | 0.37 | Most buildings roofed & finishes in progress, subcontracted works still at superstructure level. External works not yet commenced. |
Construction of Margaret Mwachiyeya Boarding Secondary School | Lusaka | Chongwe | Zambia Nonferous Metals | 0.6 | Operational; Contractor attending to snags. |
Construction of Lusaka West Boarding Secondary School | Lusaka | Kafue | Fair Face | 0.69 | Most buildings roofed, others at finishes level, while external works were also in progress. |
Constructiion of Sikongo Boarding High School | Western | Kalabo | China Gansu Engineering | 0.96 | External works still being done, & few finishes. |
Constructiion of Libonda Boarding High School | Western | Kalabo | China Jiangxi | 0.49 | Houses & Adminstration block roofed & plastered; school hall & library at gable levels; Others buildings not yet commenced; to consider high rise buildings due to limited space. |
Construction of Ikelenge Boarding Secondary School | Northwestern | Ikelenge | Kegon Services Limited | 0.16 | Most buildings were at superstructure level & external works not yet commenced. |
Construction of Liyovu Boarding Secondary School | Northwestern | Zambezi | Hua Jiang Investments | 0.14 | Establishment of site offices done, Site cleared. Contractor considering partnering with another contractor to execute the contract. |
Construction of Mako Boarding Secondary School | Northwestern | Kasempa | T&H Eminence | 0.27 | Most buildings were at superstructure level, some were already at gable level awaiting roofing. Hostels blocks & dining/ kitchen were still at substructure level.. |
Construction of Kampamba Day High School | Muchinga | Mpika | Heros Construction | 0.35 | All buildings have been roofed, except slab which is at slab level. |
Construction of Chewe Shimfwamba Day High School | Muchinga | Mpika | Nelkan industrial const. ltd | 0.49 | Most of buildings were roofed, others at superstructure, except assembly hall which was still at substructure. |
Construction of John Mubanga Day High School | Muchinga | Mpika | Heros Construction | 0.31 | All buildings were at gable level, except tuck shop & sports hall which were still at substructure. |
Construction of Kopa Day High School in Nothern Province | Muchinga | Mpika | Nelkan industrial const. ltd | 0.43 | All houses at gable levels, except sports hall still at substructure. |
Construction of Nakonde Day High School | Muchinga | Nakonde | Savenda | 0.38 | Most buildings have been roofed, while others were at gable level. External works not yet commenced. |
Construction of Katibunga Boarding Secondary School | Muchinga | Mpika | Shanai & Matty Joint Venture | 0.32 | All buildings were at gable level. |
Construction of Michael Sata Boarding Secondary School | Muchinga | Isoka | Covec Zambia Limited | 0.14 | Houses at superstructure level; while other buildings are at substructure level. |
Construction of Matumbo Boarding Secondary School | Muchinga | Shiwa ngandu | Covec Zambia Limited | 0.2 | Most buildings were at slab and superstructure block work levels, excerpt assembly hall and dining /kitchen which were still at substructure levels. |
Construction of Chibale Boarding Secondary School | Muchinga | Chama | Kegon Services Limited | 0.17 | Most buildings roofed, , while others at gable level, external works also in progress. |
Construction of Chama South Boarding Secondary School | Muchinga | Chama | China Jiangxi | 0.93 | Operational; Contractor working on snags. |
Construction of Chikando Day High School | Eastern | Chipata | Marike | 0.27 | Recommended for termination |
Construction of Chiparamba Girls’ Secondary school | Eastern | Chipata | Hua Chang | 0.91 | Contractor attending to snags; External works still in progress. |
Construction of Chikowa day Secondary School | Eastern | Nymba | Saltech Enterprises | 0.72 | Contractor attending to snags; External works still in progress. |
Construction of Chasefu Boarding Boarding Secondary School | Eastern | Lundazi | China Jiangxi | 0.34 | All houses & tuckshop roofed, while other buildings were at gable- levels, & school hall at substructure level. |
Construction of Kacholola Boarding Boarding Secondary School | Eastern | Nyimba | China Jiangxi | 0.76 | Operational; External works still in progress |
Construction of Vubwi Day Secondary School | Eastern | Vubwi | China Gansu | 0.41 | All buildings roofed & plastered except assembly hall at gable level . While external works are in progress. |
Construction of Sinda Day Secondary School | Eastern | Sinda | Zhong Mei | 0.31 | All buildings roofed and plastering in progress, while external works not yet commenced. |
Construction of Nalolo Boarding Secondary School | Western | Sennga | China Gansu | 0.4 | All houses roofed, other building at super structure level. |
Construction of Limulunga Day Secondary School | Western | Mongu | Zhogmei | 0.66 | Most buildings were at roof level, while external works not yet commenced. |
Construction of Mayukwayukwa Boarding Secondary School | Western | Kaoma | Hua Jiang Investments | 0.89 | Operational; sports fields still in progress, oxidation ponds must be redone. |
Construction of Mitete Boarding Secondary School | Western | Lukulu | China Jiangxi | 0.22 | Most buildings were at superstructure, others slab level, while only few at substructure. |
Construction of Sinazongwe Day High School | Southern | Sinazongwe | Marike | 0.34 | Recommended for termination |
Construction of Shungu Namutima Day Secondary School | Southern | Livingstone | Mango Tree | 0.43 | All buildings, roofed, awaiting finishes and external works. |
Construction of Ndondi Boarding Secondary School | Southern | Choma | Datang International Engineering | 0.34 | Most of the buildings were at gable level while few were still at slab. External works not yet commenced. |
Construction of Kaumba Boarding Secondary School | Southern | Monze | Millers | 0.67 | Operational; contractor working on snags & external works. |
Construction of Gabion wall at Kaumba Boarding Secondary School | Southern | Kazungula | Zamchin | 0.98 | Completed; awaiting final inspection |
| | | | | |