Project NameLocation Name of ContractorPercentage (%) of Work DoneComments
ProvinceDistrict
Construction of Mushindamo Girls Tech Boarding High SchoolNorthwesternSolweziHua-Jiang Investments0.79Operational; contractor attending to snags;  Sports fields being done.
Construction of Chavuma Boarding High SchoolNorthwesternChavumaHua-Jiang Investments0.67Operational; Contractor working on snags, Sewerline to be redone.
Construction of Kanyama Boarding High SchoolNorthwesternMwinilungaHua-Jiang Investments0.75Operational; Contractor working on snags, connecting water from the river as additional works,  and construction of oxidation ponds to be done.
Construction of Kayombo Boarding High SchoolNorthwesternKabompoChina Jiangxi0.93Operational; Using genset, contractor attending to snags.
Construction of Mufumbwe Boarding High School (Phase II)NorthwesternMufumbweJizan0.56Operational; Buildings at finishes level and  external works yet to be done.
Construction of Kaputa Boarding High SchoolNorthernKaputaHua-Jiang Investments0.69Operational; external works still in progress;  Sports fields not yet done
Construction of Lupososhi Boarding High SchoolNorthernLuwinguHua-Jiang Investments0.6Operational;Contractor attending to the snags; and also on external engineering services.
Construction of Chilubi Boarding High SchoolNorthernChilubiHua-Jiang Investments0.7Operational; Contractor working on fininishes  to the buildings  and  also constructing  external engineering services..
Construction of Lunte Girls Technical Boarding High School (Phase1)NorthernMporokosoWah Kong0.92Operational;External works still in progress, contractor attending to snags..
Construction of External Works at Lunte Girls Technical Boarding High School.NorthernMporokosoWah Kong0.17Operational;External works still in progress.
Construction of Menje Boarding High SchoolNorthernMbalaSavenda0.63Most of houses roofed, learning area buildings at superstructure level.
Construction  External Works at  Menje Boarding High SchoolNorthernMbalaSavenda0.2External works in progress.
Construction of Ntumpa Boarding High SchoolNorthernKasamaHua-Jiang Investments0.68Operational; Contractor attending to snags..
Construction of External Works at  Ntumpa Boarding High SchoolNorthernKasamaHua-Jiang Investments0.32Operational;External works still in progress.
Construction of Milenge Boarding High SchoolLuapulaMilengeHua-Jiang Investments0.82Operational; Attending to snags, sports fields not yet done..
Construction of Kapale Boarding High SchoolLuapulaNchelengeHua-Jiang Investments0.81Finishes and painting works in progress.
Construction of External Works at Kapale Boarding High SchoolLuapulaNchelengeHua-Jiang Investments0.26External works still in progess
Construction of Kashita Day  High SchoolLuapulaMwansabombweChina Gansu Engineering0.7Operational, external works still in progress.
Construction of Moomba Boarding High SchoolCentralChibomboHua-Jiang Investments0.63Operational;  Oxidational ponds and  Sports fields not yet done, school negotiating for land..
Construction of Kapiri Mposhi Day High SchoolCentralKapiri MposhiZaminliny0.84Operational;  Contractor attending to snags, school negotiating for land to build oxidation ponds.
Construction of Kapiri  girls’ Tech School Secondary SchoolCentralKapiri MposhiWah Kong0.85 Operational;  high iron content in water to be ressolved; sports fields not done.
Construction of Kafushi Boarding Secondary SchoolCentralChibomboCovec0.92 Operational;  Contractor attending to snags; sports fields not done yet.
Construction of Itezhitezhi Boarding Secondary SchoolCentralItezhitezhiHua-Jiang Investments0.82Operational; external works still in progress. Sports fields not yet done.
Construction of Justin Mukando Boarding High School (Phase 2)CentralSerenjeHua-Jiang Investments0.62Operational; Plumbing works not completed to kitching dining  hall, contractor attending to snags, Sports fields not yet completed.
Construction of Chipepo Secondary SchoolCentralKapri MposhiHua-Jiang Investments0.9Operational; Oxidation poinds excavated not yet lined with concrete;Sports fields in progress, school using genset not yet connected to (zesco) National Grid.
Construction of Muyombe Boarding High School (Phase 2)MuchingaMafingaCovec0.84Operational water, sewer reticulation and oxidation ponds under construction
Construction of Mandevu Day High School  ( in Luangwa)LusakaLuangwaDatong0.87Operational; Attending to snags.
Construction of Kabanana Day Secondary SchoolLusakaLusakaASSESCO0.64Operational;  Attending to snags, external works in progress.
Construction of Chiware Boarding High School (Phase 1)EasternNyimbaWah Kong0.68 Operational; Contractor attending to snags & working on external works.
Construction of Mutumbata day High SchoolEasternPetauke,Mango Tree Construction Ltd0.62 Operational; Oxidation ponds under construction.
Construction of Kapoche Boarding High SchoolEasternKateteMango Tree Construction Ltd0.78 Operational; contractor attending to snags.
Construction of Mumbi Boarding High SchoolEasternPetauke,Zamchin0.53Finishes under construction, while external works not yet commenced.
Construction of Lukulu Boarding High SchoolWesternLukuluChina Jiangxi0.79Operational; Attending to snags, External works in progress
Construction of Nakaanya Girls Tech Boarding High SchoolWesternMonguHua-Jiang Investments0.92Operational; Contractor attending to snags, while external works are still in progress.
Construction of Nangweshi Boarding High SchoolWesternShang’omboChina Jiangxi0.77 Operational; Contractor attending to snags, external works  in progress. Septic & soak aways done, geneset available not installed, sports field not done space not adequate.
Construction of Munyumbwe Boarding HighSouthernGwembeHua-Jiang Investments0.8 Operational; Contractor attending to snags; Oxidation ponds & sports fields under construction.
Construction of Batoka Boarding High SchoolSouthernChomaCovec0.71 Operational; Contractor attending to snags, sports fields done except football pitch.
Construction of Musa Day High SchoolNorthernKasamaAssociated Electrical and Sales Contractors0.31All buildings roofed, except school hall which is at superstructure. External works not yet commenced.
Construction of Bweupe Boarding Secondary SchoolNorthernMporokosoHua Jiang Investments0.16Most of buildings were at superstructure level.
Construction of Nsama Boarding Secondary SchoolNorthernNsamaHua Chang0.39Learning area buildings at superstructure level & some houses have been roofed.
Mungwi Girls Boarding Secondary SchoolNorthernMungwiAfrican Brothers0.35All buildings roofed & finishes in progress.
Construction of Katuta Boarding Secondary SchoolNorthernLuwinguHua Jiang Investments0.21All buildings at Superstructure level.
Construction of Kasaba Day High SchoolLuapulaSamfyaASESCO0.16Some buildings roofed, while some at superstructure -level. External works not yet commenced.
Construction of Kalanga Day Secondary SchoolLuapulaMansaMelt Cast/ Geo tech joint venture0.42Most building roofed & finishes in progress, while external works not yet commenced.
Construction of Chembe Boarding Secondary SchoolLuapulaCheembePowerflex0.24Almost all buildings were at gable level, while gilrls’ dormitories were roofed. External works not yet commenced.
Construction of Mweenda Boarding Secondary SchoolLuapulaChipiliChina Henan0.25Most buildings were at superstructure level, except assembly hall which was still at substructure level.
Construction of Pambashe Boarding Secondary SchoolLuapulaKawambwaChina Gansu0.35Most of the buildings were roofed & finishes were in progress. External works not yet commenced.
Construction of Kalungwishi Boarding Secondary SchoolLuapulaChiengeFlourishing0.43Recommended for termination; some buildings were at superstructure level while others were still at substructure level. Ezxternal works not commenced.
Construction of Kanona Day High SchoolCentralSerenjeSavenda0.58All buildings roofed except,  assembly hall still at substructure level.
Construction of Mumbwa Day High SchoolCentralMumbwaZ-Con0.27All buildings were at superstructure -level; external works not yet commenced.
Construction of Chibale Day High SchoolCentralSerenjeASESCO0.37Teachers houses roofed and plastered, other buildings at supperstructure level, except for assembly hall at substructture level.
Construction of Mailo Boarding Secondary  SchoolCentralSerenjeSavenda0.62All buildings roofed, excpt assembly hall and dining kitchen.
Construction of External works at Mailo boarding Secondary SchoolCentralSerenjeSavenda0.21External works in progress.
Construction of Mkushi South Boarding Secondary SchoolCentralLuanoSavenda0.17Most buildings were at substructure level , while a few were at superstructure level. External works not yet commenced.
Construction of Makululu Day Secondary SchoolCentralKabweBSBK Joint Venture0.38Operational; All buildings roofed, and external works in progress.
Construction of Muchinda Boarding Secondary SchoolCentralSerenjeSaltech Enterprises Limited0.2Five houses were roofed, while most other buildings were at gable level, except assembly hall which was at substructure level. External works not commenced yet.
Construction of Fisenge Day High SchoolCopperbeltLuanshyaShaftex0.4Operational; Most buildings were at finishes level, assembly hall not roofed & external works in progress..
Construction of Chati South Boarding Secondary SchoolCopperbeltKalulushiPlinth0.06Finishes to building in progress, & external works were in progress.
Construction of Mulundu Day Secondary SchoolCopperbeltMufuliraCovec Zambia Limited0.29Most buildings were at superstructure level, except assembly hall which was still at substructure level.
Construction of Lumpuma Boarding Secondary SchoolCopperbeltLufwanyamaDatong Construction0.15Most of buildings were at superstructure level while a few were still at substructure level.
Construction of Luansobe Boarding Secondary SchoolCopperbeltMasaitiEarthrow Investments Limited0.19Some of builldings were at superstructure level, while others are at substructure level.
Construction of Munali Centre of Excellence for special education needsLusakaLusakaChina Jiangxi0.5some buildings roofed; Others were at gable level while external works were not yet commenced.
Construction of Faith Baptist Community SchoolLusakaLusakaHua Chang0.52All buildings roofed & platered; External works in progress.
Construction of Chikupi Day Secondary SchoolLusakaKafueDong Da0.37Most buildings roofed & finishes in progress, subcontracted works still at superstructure level. External works not yet commenced.
Construction of Margaret Mwachiyeya Boarding Secondary SchoolLusakaChongweZambia Nonferous Metals0.6Operational; Contractor attending to snags.
Construction of Lusaka West Boarding Secondary SchoolLusakaKafueFair Face0.69Most buildings roofed, others at finishes level, while external works were also in progress.
Constructiion of Sikongo Boarding High SchoolWesternKalaboChina Gansu Engineering0.96External works still being done, & few finishes.
Constructiion of Libonda Boarding High SchoolWesternKalaboChina Jiangxi0.49Houses & Adminstration block roofed & plastered; school hall & library at gable levels; Others buildings not yet commenced; to consider high rise buildings due to limited space.
Construction of Ikelenge Boarding Secondary SchoolNorthwesternIkelengeKegon Services Limited0.16Most buildings were at superstructure  level & external works not yet commenced.
Construction of Liyovu Boarding Secondary SchoolNorthwesternZambeziHua Jiang Investments0.14Establishment of site offices done, Site cleared. Contractor considering partnering with another contractor to execute the contract.
Construction of Mako Boarding Secondary SchoolNorthwesternKasempaT&H Eminence0.27Most buildings were at superstructure level, some were already at gable level awaiting roofing. Hostels blocks & dining/ kitchen were still at substructure level..
Construction of Kampamba Day High SchoolMuchingaMpikaHeros Construction0.35All buildings have been roofed, except slab which is at slab level.
Construction of Chewe Shimfwamba Day High SchoolMuchingaMpikaNelkan industrial const. ltd0.49Most of buildings were roofed, others at superstructure, except assembly hall which was still at substructure.
Construction of John Mubanga Day High SchoolMuchingaMpikaHeros Construction0.31All buildings were at gable level, except tuck shop & sports hall which were still at substructure.
Construction of Kopa Day High School in Nothern ProvinceMuchingaMpikaNelkan industrial const. ltd0.43All houses at gable levels, except sports hall still at substructure.
Construction of Nakonde Day High SchoolMuchingaNakondeSavenda0.38Most buildings have been roofed, while others were at gable level. External works not yet commenced.
Construction of Katibunga Boarding Secondary SchoolMuchingaMpikaShanai & Matty Joint Venture0.32All buildings were at gable level.
Construction of Michael Sata Boarding Secondary SchoolMuchingaIsokaCovec Zambia Limited0.14Houses at superstructure level; while other buildings are at substructure level.
Construction of Matumbo Boarding Secondary SchoolMuchingaShiwa nganduCovec Zambia Limited0.2Most buildings were at slab and superstructure block work levels, excerpt assembly hall and dining /kitchen which were still at substructure levels.
Construction of Chibale Boarding Secondary SchoolMuchingaChamaKegon Services Limited0.17Most buildings roofed, , while others at gable level, external works also in progress.
Construction of Chama South Boarding Secondary SchoolMuchingaChamaChina Jiangxi0.93 Operational; Contractor working on snags.
Construction of Chikando Day High SchoolEasternChipataMarike0.27Recommended for termination
Construction of Chiparamba Girls’ Secondary schoolEasternChipataHua Chang0.91Contractor attending to snags; External works still in progress.
Construction of Chikowa day Secondary SchoolEasternNymbaSaltech Enterprises0.72Contractor attending to snags; External works still in progress.
Construction of Chasefu Boarding Boarding Secondary SchoolEasternLundaziChina Jiangxi0.34All houses & tuckshop roofed, while other buildings were at gable- levels, & school hall at substructure level.
Construction of Kacholola Boarding Boarding Secondary SchoolEasternNyimbaChina Jiangxi0.76 Operational;  External works still in progress
Construction of Vubwi Day Secondary SchoolEasternVubwiChina Gansu0.41All buildings  roofed & plastered except assembly hall at gable level . While external works are in progress.
Construction of Sinda Day Secondary SchoolEasternSindaZhong Mei0.31All buildings roofed and plastering in progress, while external works not yet commenced.
Construction of Nalolo Boarding Secondary SchoolWesternSenngaChina Gansu0.4All houses roofed, other building at super structure level.
Construction of Limulunga Day Secondary SchoolWesternMonguZhogmei0.66Most buildings were at roof level, while external works not yet commenced.
Construction of Mayukwayukwa Boarding Secondary SchoolWesternKaomaHua Jiang Investments0.89 Operational; sports fields  still in progress, oxidation ponds must be redone.
Construction of Mitete Boarding Secondary SchoolWesternLukuluChina Jiangxi0.22Most buildings were at superstructure, others slab level, while only few at substructure.
Construction of Sinazongwe Day High SchoolSouthernSinazongweMarike0.34Recommended for termination
Construction of Shungu Namutima Day Secondary SchoolSouthernLivingstoneMango Tree0.43All buildings, roofed, awaiting finishes and external works.
Construction of Ndondi Boarding Secondary SchoolSouthernChomaDatang International Engineering0.34Most of the buildings were at gable level while few were still at slab. External works not yet commenced.
Construction of Kaumba Boarding Secondary SchoolSouthernMonzeMillers0.67Operational; contractor working on snags & external works.
Construction of Gabion wall at Kaumba Boarding Secondary SchoolSouthernKazungulaZamchin0.98Completed; awaiting final inspection